Most battery-related warranty calls trace back to a handful of predictable oversights at commissioning. A short, repeatable checklist protects both the system and your service schedule.

Battery commissioning checklist: DC polarity, terminal torque, firmware version, serial log and photo evidence
Battery commissioning checklist: DC polarity, terminal torque, firmware version, serial log and photo evidence

The checklist

  • Verify DC polarity and torque on every terminal before first energisation.
  • Confirm firmware versions on inverter and battery management system.
  • Record battery serial numbers and installation date in the commissioning report.

Photograph the installed system and attach it to the report. Six months later, that photo is the fastest way to close a support case.

Commissioning StepTarget Measurement / SettingPass Criteria before Handover
1. DC Polarity & Terminal TorqueMultimeter V_dc check (breaker open) + calibrated torque wrench (Nm)M8/M10 busbar & battery terminals torqued to 8–14 Nm per datasheet; zero reverse polarity
2. CAN-Bus / RS485 BMS LinkRJ45 pinout check (Type A vs Type B) + 120 Ω termination resistorInverter/GX displays real-time BMS SoC (%), cell temperature (°C), and CVL/CCL/DCL limits
3. Smart Meter CT OrientationVerify K→L arrow towards load/grid per manual + phase sequence L1/L2/L3Positive grid import when AC load is switched on; battery discharges to zero out grid meter
4. Firmware & Serial LogUpdate inverter + BMS to matched release; photograph nameplate & wiringArchive serial numbers, firmware versions, and photos in customer commissioning dossier

B2B Technical Documentation & Pallet Dispatch Desk

Access official manufacturer datasheets, EU grid certificates, and full-pallet trade pricing across Spain and Portugal.

Frequently Asked Questions (FAQ)

Where can I check real-time B2B stock and pallet quantities?+

Log in to your PV-PARTNER installer account or contact our sales engineering desk for immediate stock and pallet quotes.

Are official manufacturer datasheets and grid certificates included?+

Yes, all tier-1 solar panels, inverters, and batteries in our catalog carry downloadable datasheets and European compliance certificates.

How do I request a custom B2B quote for a commercial or multi-pallet project?+

Use the Request Project Quote button to reach our team on the Contact page or call our Spain and Portugal support lines directly.


Author: Virginie Paulo (Senior PV Distribution & Regulatory Specialist) · Technical review: Hendryk Knuth (Technical Director, PV-PARTNER / YOFI SUN S.L.) · Regulatory & technical verification date: 4 November 2026. Prepared with AI-assisted drafting and verified against primary BOE, DGEG, and manufacturer documentation.

UPAC paperwork in Portugal: a short checklist
The minimum paperwork chain for small self-consumption units.